Courtesy of SRF
Travel impacts as of August 9, 2018:
Lane Closure of 34 St S from 4 Av S to 12 Av S
The northbound lanes of 34 St S will reopen today at 6:00 p.m.
Lane Closure – Right lane heading northbound 21 St from railroad tracks at SE Main Av Intersection to 4 Av S
Watermain relocation underway on the east side of 21 St, north of the railroad tracks
Road Closure at 22 St S and 4 Av S from 21 St to 22 St S
Underground utility work underway
Construction Progress:
Ames continues to install new watermain north of 4 Av along 22 St. On 4 Av, road, sidewalk, and tree removal operations continue along with watermain installation and sanitary sewer operations. Tree removal operations are underway north of the high school parking lot and south of 1 Av.
Looking ahead:
Watermain operations will continue along 22 St. Once installed, Ames will begin installation of the forcemain for the storm sewer. Removal operations will continue along 21 St north of 4 Av and north of the high school. A temporary signal is being installed at 4 Av and 34 St.
Please note that conditions and road closures may change with short notice. For the most up-to-date information, please register to receive direct e-mail updates. You may also check for information at http://cityofmoorhead.com/underpass.
To learn about other public construction projects in the City of Moorhead, visit the Current Projects Map at www.cityofmoorhead.com to read more about upcoming projects including maps, project scope, current status, and traffic impacts.